Project Data

Location: Dallas, Texas
Applications: Primary Clarifier Sulfide Removal, Wastewater Treatment Optimization
02 Supply: LOX Storage Tank
02 Capacity: 14000 lbs / day
Project Consultant: Alan Plummer & Assoc.
ECO2 Project - Dallas, Texas

Project Summary

Alan Plummer & Associates researched several oxygenation technologies before selecting a large scale ECO2 system to inject 10 mg/L of dissolved oxygen to the plant’s 150MGD influent pump station. The system completely dissolves pure oxygen to oxidize dissolved sulfides and reduce H2S gas levels observed at the clarifier surface. With all oxygen completely dissolved on a side stream, the settling process in the clarifiers is undisturbed.