Spring Creek Lift Station

The sewer collection system in the City of Edmond, OK, includes two long force mains with high H₂S formation potential, which have caused significant odor and corrosion issues.

At a Glance

About the Project

System
Speece Cone®
Place
Edmond
State or country
Oklahoma
Oxygen capacity
775 lbs/day (352 kg/day)
Installed
2018
Consultant
Freese and Nichols

After the successful installation at the Chisholm Creek Lift Station, a second ECO₂ system was installed at the Spring Creek Lift Station to treat the 20" diameter, 3-mile-long force main. The Speece Cone system dissolves enough oxygen to sustain aerobic conditions throughout the force main, reducing H₂S formation and release.

The Next Step

Planning a Similar System?

Send your flows and the oxygen demand for a system like Spring Creek Lift Station. ECO₂ sizes the cone and returns a budgetary price, and its engineers can share more data on Spring Creek Lift Station for a submittal.

A stainless steel Speece Cone with its side stream pump and controls at a fenced pump station among pine trees