Savannah Harbor Upgrade Tackles Multiple Tasks

An ENR Southeast article on deepening Savannah's harbor, and on the dissolved oxygen system with Speece Cones® chosen from over 20 technologies to protect the river.

Details

Publisher
ENR Southeast
Published
May 2017
Author
Jim Parsons

Summary

An ENR Southeast article by Jim Parsons on the Savannah Harbor Expansion Project (SHEP), the joint effort of the U.S. Army Corps of Engineers' Savannah District and the state of Georgia to deepen the river for larger ships using the widened Panama Canal. The cost estimate had grown from $706 million to $973 million, and about half of it went to environmental mitigation worked out over 17 years. Dredging nearly 24 million cubic yards would lower the channel by 5 ft to a mean low water depth of 47 ft. Chosen from more than 20 technologies, it uses Speece Cones and will draw about 150 million gallons of river water a day. Other elements include a 97 million gallon raw water impoundment to protect Savannah's drinking water from chloride, removal of a 1970s tide gate to protect freshwater marsh, a planned fish passage and the recovery of the Civil War ironclad CSS Georgia. The article closes on cost growth of nearly 40%, a schedule pushed to at least 2020, and the port's new cranes.

Key Figures

Questions

How was the technology chosen?

Speece Cones were selected from more than 20 potential technologies as the cost-effective way to hold the harbor's oxygen levels. (PDF page 1) (opens in a new tab)

What is being built?

Twelve 22 ft tall, 12 ft diameter stainless steel Speece Cones at two sites, drawing about 150 million gallons of river water a day. (PDF page 1) (opens in a new tab)

The Project

Savannah Harbor Expansion

Location
Savannah, Georgia
Application
River Water Quality
Capacity
40,000 lbs/day
See the Project

In Full

More Key Figures

Two more, each with what it measures and its PDF page.

From the PDF

FigureWhat It Measures
$973 million USD
Revised SHEP cost estimate, up from $706 million (PDF page 1 (opens in a new tab))
47 ft
Mean low water depth after dredging (PDF page 1 (opens in a new tab))

How to Cite

One line to paste into a report.

Jim Parsons. Savannah Harbor Upgrade Tackles Multiple Tasks. ENR Southeast, May 2017. Project engineer: Amec Foster Wheeler, CDM, U.S. Army Corps of Engineers. Eco Oxygen Technologies Technical Library. https://eco2tech.com/technical-library/savannah-harbor-upgrade-tackles-multiple-tasks/

https://eco2tech.com/technical-library/savannah-harbor-upgrade-tackles-multiple-tasks/

The Next Step

Ask an ECO₂ Engineer

Questions about this published article, or about your own water? An application engineer answers, with the figures.

A row of stainless steel Speece Cones with ECO₂ signs on the Savannah River, Georgia