Projects

Pump Station 1

Project Data

Location: Scarborough, Maine
Applications: Wastewater H₂S Prevention
02 Supply: LOX Storage Tank
02 Capacity: 80 lbs / day
Project Consultant: Internal
ECO2 Project - Scarborough, Maine

Project Summary

With low flows and long retention times, this pump station was the ideal location for superoxygenation. The high pressure in the line allows for enough oxygen to be dissolved to carry through the 8-hour retention time to prevent H2S at the discharge of this 1-mile long force main.

Related Projects